Friday 27 May 2016

GOLDBECK Solar completes 50 MW PV power plant in Melksham, England

 GOLDBECK Solar has already  constructed more than 500 PV power plants
GOLDBECK Solar GmbH (Hirschberg, Germany) connected the Sandridge Solar Park to the grid on schedule at the end of March. The 49.6 MWp ground-mounted plant in Melksham (Wiltshire, UK) was constructed within 4 months.
In addition to overseeing the plant’s construction, GOLDBECK managed the planning and implementation of the associated 132 kV substation. The project was fully financed by GOLDBECK, the company reports.

Solar modules from S-Energy and Canadian Sola
This is the largest photovoltaic project constructed by the general contractor to-date, with Parley Solar Park in Bournemouth (37.3 MWp) being its next largest. Main project components include inverter stations from Schneider and solar modules from S-Energy and Canadian Solar.
“GOLDBECK continues to demonstrate the reliability and customer-oriented flexibility of its technological spectrum,” commented Joachim Goldbeck, Managing Director of GOLDBECK Solar GmbH.
The company has already  constructed more than 500 PV power plants, with approximately 600 MWp in operation.
source:http://www.solarserver.com

No comments:

Post a Comment